Dangerous goods storage yard there is a hidden danger, Shenzhen four big docks are on the "blacklist", be listed and supervised!

Besson 2020-09-30 20:07:56

A few days ago, the safety production inspection team of the Security Committee Office of the Ministry of Transport inspected the safety production of the port. Shenzhen Port was listed for supervision and 7 storage yards were named.

Notice from the Department of Transportation of Guangdong Province on the Supervision of the Listing of Major Production Safety Accidents at the Shenzhen Port Dangerous Goods Container Yard:

Shenzhen Municipal Transportation Bureau:

On September 18, the Work Safety Inspection Team of the Office of the Security Committee of the Ministry of Transport reported to our department that the inspection found problems and pointed out: the environmental protection, fire protection, occupational health and other facilities and equipment of the 7 dangerous goods container yards in Shenzhen Port failed to pass the acceptance or Recorded and put into use is a major hidden danger of production safety accidents.

In accordance with the "Guangdong Province Major Production Safety Accidents Management and Listing Supervision Measures", our department has decided to implement listing supervision for the major accidents. The specific requirements are as follows:

1. Basic situation of major hidden dangers

(1) The name of the hidden danger The safety production conditions of the dangerous goods container yard of Shenzhen Port do not meet the requirements of laws and regulations

(2) The production and business units involved and their specific locations

1. 13E and 13F Yard of Yantian Phase III International Container Terminal Co., Ltd.

2. Shekou Container Terminal Co., Ltd. 1C Yard

3. Anxunjie Container Terminal (Shenzhen) Co., Ltd. 8B Yard

4. Chiwan Container Terminal Co., Ltd. 03E Yard

5. 22H yard of Shenzhen Mawan Port Co., Ltd.

6. Shenzhen Dachanwan Modern Port Development Co., Ltd. H01 Yard

(3) Type of industry

Transportation, storage and postal industry

(4) Violated laws, regulations and standards

The environmental protection, fire protection, occupational health and safety facilities of the 7 dangerous goods container yards of the 6 companies mentioned above have not been accepted or filed as required and have been put into use, which violates the "Port Engineering Construction Management Regulations" and the "Port Operation Management Regulations", but also The work requirements of the General Office of the State Council on the “Comprehensive Management Plan for the Safety of Hazardous Chemicals (2016-2018)” and the “Special Action Plan for the Safety Management of Dangerous Goods Port Operations (2016-2018)” of the General Office of the State Council have not been completed on time .

2. Supervise specific matters

(1) Your bureau shall urge the above-mentioned enterprises to immediately stop the storage of dangerous goods in categories 1 to 7 (except for item 2.2), and immediately clear the existing categories 1 to 7 (except for item 2.2) in the yard ) Dangerous cargo containers.

(2) Your bureau shall urge the above-mentioned enterprises to increase the necessary safety protection measures, and to ensure that the safety measures are implemented, the dangerous goods of item 2.2, category 8 and category 9 shall be stored in accordance with the limit of the safety status assessment report.

If an unlimited amount is required in the safety status assessment report, the maximum stockpiled amount during the listing supervision period shall not exceed the actual stockpiled amount of the same category on September 17, 2020.

(3) Your bureau should immediately report to the Shenzhen Municipal People's Government on a special topic, and ask the Municipal People's Government to coordinate the environmental protection, housing construction, health, and transportation departments as soon as possible to speed up the processing of relevant procedures.

3. Processing period

(1) Rectification period: from now until December 31, 2020.

(2) The corporate governance plan and your bureau's promotion plan should be reported to our department before September 27, and the progress of governance and promotion will be reported to our department every ten days.

4. Methods and procedures for listing supervision and cancellation

If your organization has completed the relevant work in accordance with the above requirements, and meets the following requirements: the involved enterprise's environmental protection, fire protection, occupational health and other related facilities and equipment have been rectified and passed the acceptance or filing as required.

During the period when the enterprises involved were supervised, there were no general and above safety production liability accidents involving casualties. Your bureau can submit to our department an application for cancellation of the listing supervision, a report on the rectification work, and the documents and materials formed in the rectification work within 7 working days before the expiration of the listing supervision period.

Our office will check the application materials within 5 working days according to the application situation, and the listing supervision will be cancelled if the above conditions are met after review.